In keeping with its client-focused objectives, PNR has developed expertise in the design and installation of steel portal framed buildings.
Contracts to-date have included both open (i.e. one side open for access) and closed buildings and relocation of existing steel-framed buildings. Structures can be finished in block, brick or cladding and we can deliver all the associated infrastructure works and internal fit out works as necessary.
CASE STUDY: ACREWOOD WAY, ST. ALBANS – BUILD OF 3 STEEL PORTAL FRAMED BUILDINGS PLUS REDEVELOPMENT OF WASTE TRANSFER FACILITY
Contract Value: £830,000 (total works including building)
Contract Duration: 29 weeks
Client: Veolia Environmental Services Ltd.

PROJECT BRIEF:
PNR were appointed as principal contractor and designer to redevelop an existing operational site which had 3 redundant buildings. This involved working closely with the client to minimise any disruption to their ongoing operational requirements.
WORKS:
PNR were responsible for the design, delivery and installation of all necessary works including (phased) demolition and rebuilding of 2 steel framed industrial buildings and relocation of a third steel framed building. This included new floor slabs, drainage, mechanical and electrical works, internal push walls and all associated works.